The Site
11 March Excavation photos
12 April Slab & timber floor preparation
13 April Portico bases and pouring of concrete slabs
26 May Steel structure and timber floor stage
11 July Timber Framing
1 & 2 August Roof panel installation
Ringlands House Article
Windows installation
Foam cladding installation
15 October - Plaster lining & External Colorbond Cladding
5 November - Tiling
7 November - Deck, Kitchen and Vanities
Completed House
Newspaper Articles:
Narooma Newspaper Article 15th August 07 [pdf]
Narooma Newspaper Article 3rd October 07 [pdf]